How Long Does a Home Remodel Take in MN?

Realistic Twin Cities remodel timelines, from quote to walkthrough.

Published May 30, 2026

How Long Does a Remodel Take?

ProjectDesignPermitBuildTotal
Bathroom remodel2–4 wks1–3 wks2–4 wks6–11 wks
Kitchen remodel3–6 wks2–4 wks4–8 wks9–18 wks
Basement finish2–4 wks2–4 wks6–10 wks10–18 wks
Deck build1–2 wks1–3 wks1–2 wks3–7 wks
Whole home2–6 mo1–2 mo4–9 mo7–17 mo

What drives delays

  • Custom cabinets (8–12 wk lead)
  • Permit/inspection scheduling
  • Material backorders
  • Change orders
  • Minneapolis vs suburb permit speed

Most spring/summer remodels need contracts signed by January or February.