Published May 30, 2026
How Long Does a Remodel Take?
| Project | Design | Permit | Build | Total |
|---|---|---|---|---|
| Bathroom remodel | 2–4 wks | 1–3 wks | 2–4 wks | 6–11 wks |
| Kitchen remodel | 3–6 wks | 2–4 wks | 4–8 wks | 9–18 wks |
| Basement finish | 2–4 wks | 2–4 wks | 6–10 wks | 10–18 wks |
| Deck build | 1–2 wks | 1–3 wks | 1–2 wks | 3–7 wks |
| Whole home | 2–6 mo | 1–2 mo | 4–9 mo | 7–17 mo |
What drives delays
- Custom cabinets (8–12 wk lead)
- Permit/inspection scheduling
- Material backorders
- Change orders
- Minneapolis vs suburb permit speed
Most spring/summer remodels need contracts signed by January or February.